Issues & Change Requests
Track problems, delays and scope changes
5
Open Issues
3
Change Requests
12
Resolved This Month
₹1.4L
Change Request Value
Electrical Points Placed Incorrectly
3BHK Chennai Raised by: Ramesh M Assigned: Electrical Team 1 Jun 2025
High 2 days ago
Plywood Not Delivered – Wardrobe Blocked
Villa Interior Raised by: Suresh S Assigned: Procurement 30 May 2025
High 3 days ago
Paint Touch-up Required – Hallway Wall
Office Bangalore Raised by: Karthik S Assigned: Color Plus 31 May 2025
Medium 2 days ago
Bedroom Door Handle Loose
Villa Interior Raised by: Suresh S Assigned: ABC Carpentry 2 Jun 2025
Medium Today
Kitchen Cabinet Alignment Issue
3BHK Chennai Raised by: Ramesh M Assigned: ABC Carpentry 1 Jun 2025
Low 2 days ago
Add Crockery Unit in Dining Area
Villa Interior Requested by: Ajay Kumar (Client) 1 Jun 2025
Cost Impact: +₹45,000 Time Impact: +3 Days
Under Review
Change Wardrobe Finish – Matte to Glossy
Villa Interior Requested by: Ajay Kumar (Client) 29 May 2025
Cost Impact: +₹22,000 Time Impact: +1 Day
Approved Billed ₹22,000
Add Wallpaper in Master Bedroom
3BHK Chennai Requested by: Priya Sharma (Client) 2 Jun 2025
Cost Impact: +₹35,000 Time Impact: +2 Days
Under Review
Change Request Financial Impact
3
Total Requests
₹22K
Approved & Billed
₹80K
Pending Approval
Project Department Expected Current Delay Reason Status
3BHK Chennai Electrical 25 May 5 Jun +10 Days Wrong points placement, redo needed Active
Villa Interior Carpentry 18 May 25 May +7 Days Plywood supply delayed by vendor Recovering
3BHK Chennai Carpentry 30 May 8 Jun +9 Days Carpenter team engaged at another project Active
Villa Interior Painting 20 Jun 27 Jun +7 Days Carpentry not complete, painting can't start Projected
Laminate Not Delivered
Villa InteriorResolved: 30 May 2025Vendor delivered same day
Resolved
Kitchen Drawer Misalignment
Villa InteriorResolved: 28 May 2025Carpenter realigned
Resolved
Site Access Blocked – Security Issue
Office BangaloreResolved: 25 May 2025Coordination with client
Resolved