Projects /
Villa Interior – Pondicherry
Ajay Kumar  ·  Started: 1 May 2025  ·  Ends: 30 Aug 2025
In Progress
63%
Completion
32
Total Tasks
20
Completed
2
Open Issues
89
Days Left
Department Progress
Carpentry
78%
Electrical
40%
Plumbing
100%
Painting
20%
Flooring
90%
False Ceiling
60%
Project Info
Client
Ajay Kumar
Location
Pondicherry
Area
2200 Sq.ft
Budget
₹18,00,000
Duration
90 Days
Manager
Rajan Kumar
Pending Approvals
Living Room Design
Pending
Wardrobe Finish
Revision
Task Department Assigned To Start End Progress Status
Kitchen Cabinet Installation Carpentry
SC
ABC Carpentry
10 Jun15 Jun
70%
In Progress
TV Unit Carpentry
SC
ABC Carpentry
16 Jun18 Jun
100%
Completed
Wardrobe Installation Carpentry
SC
ABC Carpentry
20 Jun25 Jun
0%
Blocked
Electrical Wiring Electrical
EB
Bright Electricals
5 Jun12 Jun
50%
In Progress
Light Fixture Installation Electrical
EB
Bright Electricals
13 Jun15 Jun
0%
Not Started
Kitchen Plumbing Plumbing
PP
Pro Plumbers
2 Jun5 Jun
100%
Completed
Wall Painting – Living Room Painting
CP
Color Plus
25 Jun30 Jun
0%
Not Started
Project Timeline (Gantt)
Department
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Civil Work
Civil
Electrical
Electrical
Plumbing
Plumbing
False Ceiling
False Ceiling
Carpentry
Carpentry
Painting
Painting
Carpentry/Civil
Electrical
Plumbing
False Ceiling
Painting
RK
Rajan Kumar
Project Manager
Internal
MP
Meera Pillai
Interior Designer
Internal
SS
Suresh S
Site Supervisor
Internal
ABC Carpentry
Carpentry Contractor
Contractor
Bright Electricals
Electrical Contractor
Contractor
Pro Plumbers
Plumbing Contractor
Contractor
Quality Checklist
Flooring Level CheckDone
Plumbing Leak TestDone
Doors Opening SmoothlyPending
Lights & Switches WorkingPending
Paint – No PatchesPending
Furniture AlignmentPending
Hardware Fittings TightPending
Snag / Punch List
Bedroom Handle Loose
Carpentry
Open
Paint Touch-up – Hallway
Painting
Open
Kitchen Drawer Alignment
Carpentry
Fixed